Update on Cutten Green Wall Project

Park Wall has been completed.

Wall behind water well has been completed.

Wall on Hollister is substantially completed.  The last section and entrance panels should be completed by early June.

Wall on Bourgeois

  • Plans have been approved by Harris County.
  • May-June prepare and advertise for bids
  • July-August award contractor
  • September-October begin construction
  • Complete project during first quarter of 2024

These timelines are estimates and this site will be updated on a monthly basis to inform of any changes.